钢边橡胶止水带热熔机焊接时的步骤分几步走?衡水融通橡胶制品有限公司在工程施工中,经常要用到钢边橡胶止水带,一般默认钢边橡胶止水带的长度是一卷20米,但是在实际应用中,这个长度不一定比较合适,那么就需要对钢边橡胶止水带进行切割和焊接来使用,保证施工的正常进行。钢边橡胶止水带焊接需要用到止水带热熔焊机,热熔焊机分为模具和控制箱两部分组成,如何进行钢边橡胶止水带的焊接呢?
钢边橡胶止水带热熔机焊接时的步骤分几步走?
Hengshui Rongtong Rubber Products Co., Ltd. often uses steel-edged rubber water stops in engineering construction. Generally, the default length of steel-edged rubber water stops is a roll of 20 meters, but in practical application, this length is not necessarily appropriate, so it is necessary to cut and weld steel-edged rubber water stops to ensure the normal construction. Welding of steel-edged rubber water-stop strip requires hot-melt welding machine with water-stop strip. The hot-melt welding machine consists of die and control box. How to weld steel-edged rubber water-stop strip?
需要焊接的钢边止水带规格要符合要求并且检验合格,其次需要焊接的环境不能被雨淋暴晒,也不能接触污染性较强的化学物质。
1、将钢边橡胶止水带需要搭接的部分做好标记,保证中间能够塞进1cm左右的生胶片。
2、用切割机切割钢边橡胶止水带中间的橡胶,需要切30cm左右,注意不要切到钢边,然后用角磨机打磨需要搭接的橡胶部分。
钢边橡胶止水带热熔机焊接时的步骤分几步走?
3、裁剪两条生胶片堵住钢边止水带的中间圆孔不分,长度不少于5cm。
4、需要将钢边进行铆钉,用手钻在钢边上打眼,固定搭接的钢边止水带的钢边部分。
5、将预热好的热熔机的热硫化夹具垫在需要搭接的钢边止水带下,填充好生胶片。
6、安装好夹具放置千斤顶,控制热熔机温度在130-150摄氏度之间,同时用千斤顶加压,保证夹具与钢边止水带面贴合紧密,大概20分钟后取下夹具即可。